Activity is 7 days forward from today Mon, June 25, 2018           calendar
April 30, 2018 - February 15, 2019
Others
Asbury Circle Pedestrian Detour (see attachment)
It will be necessary to close the sidewalk on the south side of the CLC Project. Please see the attached plan.  Pedestrians will be detoured to the sidewalk which leads to Cox Hall. 
 
This action is required in order to complete the Campus Life Center Project.  Underground utilities must be diverted and a large underground storm water vault installed.  The detour will start on Monday April 30, 2018.  The sidewalk will remain closed until approximately mid-February of 2019.
 
Project Manager: Herzog, Alfred    Phone: 404/727-7478    email

May 29, 2018 - July 16, 2018
Road Closure
North End of Asbury Circle Closed to Vehicular Traffic (see attachment)
The north end of Asbury Circle where it connects with Eagle Row will be closed to vehicular traffic in order to make hardscape and landscape improvements.  Please see the attached plan.  Deliveries to the DUCling and Few Hall for Mail Services will use Dickey Drive.  Pedestrian detours are also shown on the attached plan.  Phase 1 of the landscape and hardscape improvements will continue through July.   Updates will be provided in the event the schedule changes.
Project Manager: Herzog, Alfred    Phone: 404/727-7478    email

June 21, 2018 - July 6, 2018
Road Closure
Eagle Row Temporary Crosswalk (see attachment)
A temporary pedestrian crosswalk will be installed on Eagle Row near the intersection of Asbury Circle (please see the attached logistics plan).  This temporary crosswalk is being installed to accommodate work for the new Campus Life Center project.  

Beginning on the evening of Thursday, June 21 temporary marking tape will be placed on Eagle Row to identify the location of the crosswalk. Work will begin at 7 p.m. and be complete by 8 p.m.  One half of the crosswalk will be placed at a time leaving one lane of travel open to vehicular traffic. Traffic flaggers will be on site to direct traffic around the work zone.  
 
The new temporary crosswalk will be put into use the morning of Friday, June 22 and directional signage will be placed nearby.  The pedestrian detour is anticipated to last approximately two weeks.   
Project Manager: Herzog, Alfred    Phone: 404/727-7478    email