Dowman Drive Summer Disruptions ---- from May 17, 2008 to October 19, 2008
A number of construction projects are scheduled on Dowman Drive this summer. The above attachment link will access a map of these projects.
Beginning mid-May, Dowman Drive will be closed between the Atwood Chemistry Building and Math and Science Building for the installation of a new steam line. This portion of Dowman Drive will reopen by mid-June.
New windows will be installed in the Administration Building starting mid-June. Staging for this work will occur between the Administration Building and White hall.
On July 7th, the Boisfeuillet Jones Visitor Parking Lot will be permanently closed for construction of the new Oxford Road Building. Visitor and accessible parking will be rerouted.
Dowman Drive entrance improvements have begun. The road will be repositioned to its original configuration through the historic gate, and the improvements will include an upgrade to the existing water line. Work will continue into October. One lane of Dowman Drive will remain open until the new entrance is complete.
Project Manager: Daniel Cook Sr.
Phone: 404.727.6145
Rollins Way to Be One-Way August 4, 2008 through September 30, 2008. ---- from August 4, 2008 to September 30, 2008
Over the next two months an extensive amount of utility work will be taking place in the vicinity of Rollins Way as new utility lines are installed and existing utility lines are relocated to make way for the new building.
In order to keep traffic flowing as smoothly as possible, as well as to provide for the safety of pedestrians and construction personnel, Rollins Way will temporarily become a one-way street beginning August 4, 2008 until September 30, 2008.
The best way to access Clifton Road from Rollins Way is to turn Right on Michael Street, and the right on Houston Mill Road.
Taking Michael Street to Clifton Road is not recommended. Left turns off of Michael Street onto Clifton Road are not permitted. We apologize in advance for any inconvenience this may cause.
Project Manager: Michael Morris
Phone: 404.727.7486
Means and Longstreet Halls Demolition ---- from August 4, 2008 to September 14, 2008
In preparation for the construction of Freshman Hall Building 4, Means and Longstreet Halls will be abated and demolished. Morely Environmental and Price & Sons will be handling the scopes for abatement and demolition, respectively. On August 4th, Price & Sons will begin to erect the site fence, which will remain in place until Freshman Hall 4 completes its construction April of 2010. This project is being managed by Carter & Associates with coordination by Planning, Design & Construction.Project Manager: Glenn Kulasiewicz
Phone: 404.727.7324